Scheduler shows not all events

Asked by Joerg Schuster

Hi,

i have sheduled 12 events from 9th march to 31th march.
The events are from 6am - 23pm - all works fine, but i only see _all_ sheduled layouts on the day, that the events was sheduled.
The calendar only shows the first three layouts and shows no the "+events" link on the other days (9,10,11,12...)

http://www.harko.at/digitalsignage/schedule.JPG

Is there any way that I can fix this?

Win XP
Client 1.2.0
Server 1.2.0

Question information

Language:
English Edit question
Status:
Solved
For:
Xibo Edit question
Assignee:
No assignee Edit question
Solved by:
Alex Harrington
Solved:
Last query:
Last reply:
Revision history for this message
Best Alex Harrington (alexharrington) said :
#1

That's how its supposed to be.

Revision history for this message
Joerg Schuster (joerg-schuster) said :
#2

Thanks Alex Harrington, that solved my question.