Auto activate task when prerequesite tasks completed?

Asked by TomL

Since a task is automatically set to inactive if it is assigned a prerequisite task, I expected it to be automatically marked active when the prerequisite task or tasks where marked completed. This doesn't appear to be supported. Is this supported somehow?
Version: 1.4.1.6611
Platform: Windows

Question information

Language:
English Edit question
Status:
Solved
For:
Task Coach Edit question
Assignee:
No assignee Edit question
Solved by:
TomL
Solved:
Last query:
Last reply:
Revision history for this message
TomL (sidared) said :
#1

From bug report:

There are two start dates, one is "planned start" the other is "actual start". The latter is marked only manually or when effort tracking is started for that task.

What you need to do is mark a "planned start" for the task. Then it will stay hidden even if the planned start is in the past until the prerequisites are done. As soon as the prereqs are done, it will show up marked "late" but only if it is past the planned start.

Cheers,
Aaron