Asked by Pablo Perez-Arias

Thank you for Task Coach. Nice, compact program. How do I mark a sub-item completed without marking the entire task and all of its other sub-items completed? Pablo

Question information

Language:
English Edit question
Status:
Solved
For:
Task Coach Edit question
Assignee:
No assignee Edit question
Solved by:
Pablo Perez-Arias
Solved:
Last query:
Last reply:
Revision history for this message
Jérôme Laheurte (fraca7) said :
#1

Marking an item completed always marks its own children completed. By default, marking the last uncompleted subitem of an item completed marks the item itself as well; this behaviour is configurable for each task ("Progress" tab) or globally ("Dates" tab in the configuration.

Revision history for this message
Pablo Perez-Arias (pperez-arias) said :
#2

That did it. Thank You.