OpenERP Addons (modules)

Planned date in Packing list form SO

Asked by Grzegorz Grzelak (OpenGLOBE.pl) on 2009-09-23

When you confirm Sales Order it generates Packing list which always contains Planned date 2 days after Sales Order. Where these dealy can be set/configured?

In Product we have "Customer Lead Time" but I have there 7 days and it have no influence on Planned dates in Picking List. Even If I want to change this date manually it is impossible because when Sales order in Confirmed created Picking list is confirmed too.

Please advice where this 2 days are set or explain how Customer Lead time works.

Question information

Language:
English Edit question
Status:
Solved
For:
OpenERP Addons Edit question
Assignee:
No assignee Edit question
Solved by:
Vinay Rana (OpenERP)
Solved:
2009-10-01
Last query:
2009-10-01
Last reply:
2009-09-24

Customer lead time is controlled from following field :
    product object form=> Procurement & Location Tab there is field Customer Lead Time which is by default 2 so it will be set 2 days by default. If you changed this in to 7 days then it will be taken 7 days as lead time.

Hope this will help.

Thanks.

Thanks. This answer assured me how Customer lead time should work. And after dipper digging I found that Security Days in Company Settings is the problem. By default OpenERP sets 7 days in Customer Lead Time and 5 days as Security days which should be added to Customer Lead Time. But they are SUBTRACTED. That's why I got 2 days lead time (7-5=2). So I converted this Answer to bug report.