Sequencing tasks in project at the time of creation of project.

Asked by dso

Hello Open ERP team

1. In 5.0.1. version when one creates a project at that time when tasks has been created, user can not give sequence to the tasks as field is in read only state !! But after creating all tasks and just by draging one task, user can have changed sequence. Which should not be there and this field should be read/write both.

2. Also there should be compulsion to first make parent task done before completing any task which is not there at present.

Thanks

Drupad

Question information

Language:
English Edit question
Status:
Answered
For:
Odoo Addons (MOVED TO GITHUB) Edit question
Assignee:
No assignee Edit question
Last query:
Last reply:
Revision history for this message
Jay Vora (Serpent Consulting Services) (jayvora) said :
#1

Hello DSO,

Your 1st query has been accepted and has been resolved in trunk.

Can you please focus more on 2nd issue?

Thanks.

Revision history for this message
dso (dso) said :
#2

Hello JVO & Open ERP team

Thank you for prompt response, let me again explain the 2nd issue :
When we create a task for project and give other task as its parent task, which should be done first before completing the task which we have been created, then system should not allowed to complete task which is created before completing its parent task. This is not happening at present in the system and any task can be done at any time.

Thanks & regards

Drupad

Revision history for this message
Jay Vora (Serpent Consulting Services) (jayvora) said :
#3

Can you please create a blueprint for this issue?

Thanks.