Same product with multiple BOMS defined - MO defaults to first BOM

Asked by Kevin McMenamin

The same inventory product can have multiple BOMs defined to allow for multiple ways of making the same product. When a SO is raised for the product, the related MO is for the first BOM - while you can change the BOM in the MO this does not update the products to be consumed, so there is no way of using an alternative BOM.

Question information

Language:
English Edit question
Status:
Expired
For:
Odoo Addons (MOVED TO GITHUB) Edit question
Assignee:
No assignee Edit question
Last query:
Last reply:
Revision history for this message
Amit Parik (amit-parik) said :
#1

Hello Kevin,

"mrp_jit" used for the "automatic run the procurement" so if the "mrp_jit" has installed then your procurement will be automatically run. This is the functionality of the mrp_jit(Just-in-time).

So if there are more then "BoM" available for one product it will consider the first "BOM" and run the procurement.
With "mrp_jit" your procurement directly goes to the "Running " state so you can not change the "BOM" on procurement.

That's why this is not a bug but functional behaviour with "mrp_jit".

For your last issue for the uninstallation , current OpenERP version does not fully supported to uninstallation.

Hope this will help for you.

Thanks