Comment 11 for bug 341687

Revision history for this message
Martin Pool (mbp) wrote : Re: [Bug 341687] Re: Manual work is required to change 'fix committed' bugs to 'fix released' when a milestone is released.

On 11 April 2011 09:38, Robert Collins <email address hidden> wrote:
> It wouldn't make it unnecessary - folk that want to see 'development
> done but not shipped' would then likely want In Progress to convert to
> Fix Released upon milestones being released.

There is definitely something there, but I don't know if it should be
automatic conversion from inprogress to fixreleased. If I have
something inprogress targeted at a milestone that released, it seems
likely that it either missed the milestone or is now fixed.